The Palo Alto new-home permit process, step by step

From the first zoning check to final inspection: Individual Review for two-story homes, mandatory deconstruction, the building permit, Public Works and utilities, and the published fees. Timelines appear only where the city publishes them.

9steps from lot check to occupancy
$16,575Individual Review fee, new two-story home
21 daysIR neighbor comment period
2-3 daysfirst response to a building pre-application
$4.79/sfschool impact fee (PAUSD)
not publishedoverall city timeline
PA-01 · Process

Nine steps to a new home

This page follows a typical teardown and rebuild of a single-family home in R-1. Projects in the single-story overlay, flood zones or historic districts have extra steps noted below. Bay Build Guide is not the city; confirm each step with Development Services, 285 Hamilton Avenue.[31]

  1. Check the lot and choose a design path

    WhoOwner, designer
    Published timingnone (self-check)
    Published feesnone
    • Look up the zone, lot size, floor-area limit, setbacks, height, daylight plane and overlays for the address (single-story overlay, FEMA flood zone, historic flag). Our address lookup uses the city parcel layer.[1,2]
    • The city's Single-Family Zoning Technical Manual explains how R-1 floor area, daylight planes and setbacks are measured.[3]
    • Decide one story or two. A one-story home in R-1 (or a home in RE) goes straight to a building permit. A new two-story home must meet all of the Two-Story Objective Design Standards; otherwise a discretionary Single Family Individual Review (IR) is required before the building permit.[4,5]
    • The city strongly encourages applicants to discuss plans with neighbors before submitting.[6]
  2. Survey, arborist and historic check

    WhoLicensed surveyor, ISA-certified arborist, historic consultant if needed
    Published timingHistoric Resource Evaluation timing: not published
    Published feesHistoric review of an IR application $1,293; demolition of a historic building $2,083 (Planning fees, Aug 17, 2026)[7]
    • Survey. The new-home building permit plan set must include a topographic/boundary survey, and the inspection list includes a setbacks/site survey inspection (code 204).[6]
    • Trees. All development projects must submit the T-1 tree disclosure sheet set; except for ADU-only projects, it must be completed by a certified arborist.[8] Protected trees include coast live, valley, blue and black oaks, big-leaf maple and incense cedar of 11.5 in. or more trunk diameter, coast redwoods of 18 in. or more, any other mature tree of 15 in. or more (excluding listed invasive and high-water-use species), street trees, heritage trees and trees designated during project review.[8] Work inside a protected tree's protection zone (radius of 10 times the trunk diameter) requires a Tree Preservation Report by an ISA-certified arborist; removing a protected tree needs a Protected Tree Removal Permit; before any site work the contractor must schedule a tree-protection verification inspection with Urban Forestry.[9]
    • Historic. Properties on the city's Historic Inventory (Category 1-2, or 3-4 downtown) and in the Professorville or Ramona Street districts are "Group A" and go to the Historic Resources Board review process. The city may require a Historic Resource Evaluation when a discretionary application proposes demolition or new construction and the existing building is more than 45 years old.[10] Most Palo Alto teardown candidates meet the age test, so check before you design.
  3. Two-story design review (Individual Review)

    WhoArchitect or designer, Planning staff and the city's consulting architect
    Published timingNotice mailed within 3 days of submittal; 21-day neighbor comment period; staff review shown as 30 days; tentative decision 10-30 days after a complete application; 14 days to request a hearing[11,12]
    Published feesIR preliminary meeting $1,193; IR for a new two-story home $16,575; Urban Forestry review $601[7]
    • Option A: design to the Two-Story Objective Design Standards (effective Feb 14, 2025) and skip IR.[5]
    • Option B: IR. A preliminary meeting with a planner and architect is optional but highly encouraged; meetings are held on Zoom on Wednesday afternoons, noon to 4 pm, after the fee is paid.[13]
    • Submit through the Accela Citizen Access pre-application; an intake appointment is required for every Planning application.[14]
    • Neighbors are notified (the flowchart shows mailing to a 150-foot radius); only adjacent neighbors may request a hearing or appeal. If no hearing is requested, the proposed decision becomes final 14 days after notice. If a hearing is requested, the director decides within 14 days of it, and the decision can be appealed to City Council.[11,12]
    • Approvals expire after 12 months unless construction has started; the director may grant one extension of up to 12 months.[11]
    • The flowchart shows the Council appeal step as 45 days; the code text in the handout says the item goes on the consent calendar within 30 days. sources differ
  4. Deconstruction permit (Palo Alto does not allow demolition)

    WhoOwner, deconstruction contractor, City-approved reuse organization
    Published timingUtility meter and service removal: 1-10 business days after applying[15]; Air District notice: at least 10 working days before work[16]
    Published feesDeconstruction intake $1,122; C&D fee $579 for single-family projects over $75,000 valuation[17]
    • Since July 1, 2020, projects that completely remove a structure must deconstruct it instead of demolishing it: a salvage survey, careful disassembly, and source separation of materials. A separate building permit is required to remove the structure.[18,19]
    • The deconstruction permit file must include the Bay Area Air District approval number (J number), a deconstruction contract signed by the owner and the deconstruction company, and a salvage survey by a City-approved reuse organization, plus the T-1 tree protection sheet and a pollution prevention plan.[20]
    • Every demolition of a load-bearing structure needs an Air District notification (J number) regardless of asbestos; for homes with four or fewer units, specific materials must be sampled and tested if they will be disturbed.[16,21]
    • Containers (bins or debris boxes) on deconstruction and construction sites must come from GreenWaste of Palo Alto.[18]
    • Before deconstruction, apply to City of Palo Alto Utilities to remove meters and service lines (Palo Alto runs its own electric, gas, water and wastewater utilities).[15]
    • Inspections: pre-deconstruction, deconstruction final, Urban Forestry tree protection verification, and a Zero Waste deconstruction consult. Moving 100 cubic yards or more of soil requires a Public Works grading permit.[20]
  5. Building permit submittal and plan check

    WhoArchitect/engineer, Project Coordinator, plan reviewers
    Published timingFirst response to a submitted pre-application within 2-3 business days[22]; plan check review time: not published
    Published feesSee fees below
    • Create an Accela Citizen Access account, file a Building Permit Pre-Application and upload three PDFs (APPLY, PLAN, DOCS). A Project Coordinator checks completeness; once complete, staff convert it to a building permit (number format XXBLD-XXXXX) and ask you to pay fees, then plan check begins.[22]
    • The PLAN file covers the Planning approval letter (IR) if any, civil plans (site, grading and drainage, topographic/boundary survey), architectural plans with exterior elevations, deconstruction plans, structural plans, CALGreen Mandatory plus Tier 2 sheet, landscape plans with the T-1 tree protection sheet, pollution prevention plan, MEP plans and Title 24 energy forms. The DOCS file holds the geotechnical report, structural calculations and green building agreement; flood-zone lots (AE, AH, AO or A) add the Public Works flood checklist.[6]
    • Energy: new single-family homes must beat the state EDR1 requirement by at least 8 points, with a Certified Energy Analyst; the all-electric requirement for new buildings was suspended on Feb 26, 2024, so mixed-fuel homes must meet electric-readiness rules.[23] The city page describes the 2023-2025 code cycle; the local 2026-2028 update status was not confirmed.
  6. Public Works, grading, stormwater and utilities

    WhoCivil engineer, Public Works Engineering, City of Palo Alto Utilities
    Published timingUtilities response about 10 business days when filed directly; Utilities inspections 3-5 business days[24]
    Published feesUtility connection charges per the standard connection fee schedule or a work-order estimate[24]
    • A grading and drainage plan with existing and proposed spot elevations is required for every new single-family home; projects creating or replacing 500 sq ft or more of impervious surface submit the Impervious Area Worksheet.[25]
    • An Excavation and Grading Permit is required when cut, fill and/or storage of soil totals 100 cubic yards or more.[26] For residential projects it is issued together with the building permit.[27]
    • Basements: perforated drain pipes around basement walls or under the slab are not allowed bay-side of Foothill Expressway; lightwells and other exterior basement spaces need a sump, pump, backflow preventer and an on-site dissipation device. If excavation needs dewatering, Public Works must approve a dewatering plan and issue a dewatering permit before any discharge.[25,27]
    • Utilities: the utility service application goes in with the building permit submittal; Utilities sets the connection charges after plans are approved and will not inspect or install before payment.[24]
  7. Fees

    WhoOwner
    Published timingFees are due when the application is converted to a permit[22]; school fees before permit issuance per the district
    Published feesTables below
    Fee (City of Palo Alto, FY 2027)Amount
    Building permit (inspection) fee, single-family, by floor area: 2,001-2,500 sf / 2,501-3,000 sf / 3,001-3,500 sf / 3,500-4,000 sf / 4,001-4,500 sf$5,139 / $5,311 / $5,824 / $5,996 / $6,167
    Base fee, single-family: up to 3,000 sf / over 3,000 sf$1,277 / $4,788
    Building plan check (single-family)125% of building permit fee
    Planning/zoning plan check; Public Works plan check (single-family)35% each
    Deconstruction intake; C&D fee (over $75,000 valuation)$1,122; $579
    Individual Review, new two-story home; IR preliminary meeting$16,575; $1,193
    Development impact fees, single family: parks; community center; libraries$18.75; $1.44; $0.86 per sq ft
    Development impact fees, single family: public safety; general government$1,383; $1,743 per unit
    Palo Alto Unified School District school impact fee, residential$4.79 per sq ft

    Sources: building and deconstruction fees[17]; planning fees[7]; impact fees[28]; school fee (rate in effect since July 9, 2022)[29]. The fee schedule does not say how the base fee and floor-area fee combine for one permit, and the impact-fee sheet does not say how credit for a demolished house is applied to a rebuild: ask Development Services. A total for a typical rebuild is not published, so we do not estimate one.

  8. Inspections

    WhoContractor, Building inspectors, Urban Forestry, Public Works, Fire
    Published timingScheduling by phone: (650) 329-2496, option 2[6]
    Published feesIncluded in the building permit fee
    • The new-home checklist lists the required inspections, including green building pre-construction, underground plumbing and electrical, setbacks/site survey (204), foundation and slab, framing and shear, daylight plane (215), insulation, drywall, roofing, electrical hot check, green building final (153), planning final (980), fire final (990), Public Works final and landscape final.[6]
    • Tree protection fencing must stay in place until the Urban Forestry final inspection; before building final, the landscape (MWELO) inspection is required.[9]
    • Underground electric services need CPAU trench and conduit inspections plus a panel inspection before connection.[24]
  9. Final and occupancy

    WhoContractor, Building Division, Utilities
    Published timingOverall time from first application to move-in: not published
    Published feesnot published
    • All final inspections on the permit card must be signed off (Building, Planning, Fire, Public Works, landscape/Urban Forestry).[6,9]
    • Gas meters are set only after Utilities receives a release from Building Inspection.[24]
    • The city publishes a Temporary Occupancy form for single-family residences.[30] The steps for the final certificate of occupancy are not published on the pages we checked.
PA-02 · Not published

What the city does not publish

  • A target or typical plan-check review time for new single-family homes.[22]
  • An end-to-end timeline from application to occupancy.
  • How the base building permit fee and the floor-area fee combine, and how impact-fee credit for a demolished house is calculated.[17,28]
  • Certificate of occupancy steps beyond the final inspections.

We do not fill these gaps with estimates. Ask Development Services at (650) 329-2496.[22]

PA-03 · Sources

Sources and last-checked dates

  1. City of Palo Alto ArcGIS: AssessorsParcels layer (zone, lot size, city-computed FAR, coverage, setbacks, height, flood and historic flags)
    City of Palo Alto GIS · last checked 2026-11-19
  2. Palo Alto Municipal Code Ch. 18.12 (R-1 district), incl. 18.12.040 Table 2 and 18.12.060 parking
    American Legal (official online code) · last checked 2026-11-19
  3. City of Palo Alto: Single-Family Zoning Technical Manual (PDF)
    City of Palo Alto · last checked 2026-11-19
  4. City of Palo Alto Planning: Forms & Applications (single-family homes, Individual Review, objective standards)
    City of Palo Alto · last checked 2026-11-19
  5. City of Palo Alto: Adopted Two-Story Development Objective Design Standards, effective Feb 14, 2025 (PDF)
    City of Palo Alto · last checked 2026-11-19
  6. City of Palo Alto: New Single-Family Residence submittal checklist (2026, PDF)
    City of Palo Alto · last checked 2026-11-19
  7. City of Palo Alto: Planning Division application fee schedule effective Aug 17, 2026 (FY27, PDF)
    City of Palo Alto · last checked 2026-11-19
  8. City of Palo Alto Urban Forestry: Tree Ordinance Information (protected trees, T-1 tree disclosure)
    City of Palo Alto · last checked 2026-11-19
  9. City of Palo Alto: T-1 Tree Protection sheet and tree disclosure statement (PDF)
    City of Palo Alto · last checked 2026-11-19
  10. City of Palo Alto: Historic Resources & Permit Review Requirements bulletin (PDF)
    City of Palo Alto · last checked 2026-11-19
  11. City of Palo Alto: IR & HIE review process handout, PAMC 18.77.075 to 18.77.090 (PDF)
    City of Palo Alto · last checked 2026-11-19
  12. City of Palo Alto: Individual Review process flowchart (PDF)
    City of Palo Alto · last checked 2026-11-19
  13. City of Palo Alto: IR preliminary review process, updated April 2026 (PDF)
    City of Palo Alto · last checked 2026-11-19
  14. City of Palo Alto: Apply for a Planning Entitlement (intake appointment required)
    City of Palo Alto · last checked 2026-11-19
  15. City of Palo Alto Utilities: Start, Stop, or Change Utilities Service (Deconstruction section)
    City of Palo Alto · last checked 2026-11-19
  16. Bay Area Air District: Asbestos Frequently Asked Questions (PDF)
    Bay Area Air District · last checked 2026-11-18
  17. City of Palo Alto: FY 2027 Adopted Municipal Fee Schedule (PDF; Development Services - Building, pp. 63-69)
    City of Palo Alto · last checked 2026-11-19
  18. City of Palo Alto Zero Waste: Deconstruction Ordinance
    City of Palo Alto · last checked 2026-11-19
  19. Palo Alto Municipal Code Ch. 5.24 Deconstruction and Construction Materials Management
    American Legal (official online code) · last checked 2026-11-19
  20. City of Palo Alto: Deconstruction/Demolition submittal checklist (7-2026, PDF)
    City of Palo Alto · last checked 2026-11-19
  21. Bay Area Air District: Regulation 11, Rule 2 (asbestos demolition, renovation)
    Bay Area Air District · last checked 2026-11-18
  22. City of Palo Alto: Apply for a Building Permit
    City of Palo Alto · last checked 2026-11-19
  23. City of Palo Alto: Green Building Code Requirements (energy reach code)
    City of Palo Alto · last checked 2026-11-19
  24. City of Palo Alto Utilities: New Connection or Upgrades to Utilities
    City of Palo Alto · last checked 2026-11-19
  25. City of Palo Alto Public Works: Residential construction requirements handout (PDF)
    City of Palo Alto · last checked 2026-11-19
  26. City of Palo Alto Public Works Engineering: Forms and Permits (Excavation and Grading Permit)
    City of Palo Alto · last checked 2026-11-19
  27. City of Palo Alto: Regulations for Groundwater Dewatering during Construction of Below Ground Structures (2021, PDF)
    City of Palo Alto · last checked 2026-11-19
  28. City of Palo Alto: Development Impact and In-Lieu Fees, as of Aug 17, 2026 (PDF)
    City of Palo Alto · last checked 2026-11-19
  29. Palo Alto Unified School District: School Impact Fees
    PAUSD · last checked 2026-11-19
  30. City of Palo Alto: Building Permit Forms (incl. Temporary Occupancy for Single Family Residential, Utility Service Application, T-1 sheet)
    City of Palo Alto · last checked 2026-11-19
  31. City of Palo Alto Urban Forestry: Development Process & Trees
    City of Palo Alto · last checked 2026-11-19