Building, remodeling or rebuilding a home in South San Francisco, CA

San Mateo County · every fact links to an official or primary source · last checked 2026-11-18

Quick answer: South San Francisco takes SB 9 lot splits and two-unit plans through the Building Division portal for ministerial review with no hearing, requires a demolition permit, and charges $121 per protected tree removal permit plus a $368 planting deposit.

On this page: Contacts · ADUs & JADUs · SB 9 · Tear down & rebuild · Remodels & additions · Fees · Seismic · Electrification & PG&E · Cost context · Not published · Sources

Building and planning contacts

ADU contact listed by the county ADU Resource Center: Planning Division, planning@ssfca.gov, (650) 877-8535
Local ADU Website
ADU Ordinance [1]

ADU and JADU rules

This table is from the San Mateo County ADU Resource Center (run by 21 Elements, a partnership of the county’s cities and the County), page updated October 30, 2026 [1]. Confirm details with the city before you design.

SizeMinimums: no ADU minimum in § 20.350.003; a JADU must be at least an efficiency unit (Health & Safety Code § 17958.1).
Maximums (interior livable space):
Detached state-mandated ADU on a single-unit lot: 800 sf
Local-standards ADU: 1,000 sf (800 sf if FAR or lot coverage limits are not met)
Converted ADU, within the existing structure, plus up to 150 sf for ingress/egress
JADU: 500 sf
State-mandated detached ADUs on multifamily lots, no size cap listed.
HeightDetached: 18 feet; up to 20 feet to match the primary dwelling’s roof pitch if within ½ mile walking distance of a major transit stop or high-quality transit corridor.
Attached: height allowed in the underlying zoning district.
SetbacksStreet side, interior side, rear: 4 feet (attached and detached).
Front: underlying zoning for local-standards ADUs; waived for state-mandated ADUs.
Distance between structures: 4 feet, including eaves, between an ADU behind the primary dwelling and other structures.
ParkingJADUs: No parking required
ADUs: 1 space per ADU or per bedroom, whichever is less; tandem or in setbacks allowed unless the Chief Planner finds it infeasible. No parking required if:
Within ½ mile walking distance from public transit;
In an architecturally and historically significant district;
Converted within existing or proposed primary residence or accessory structure;
Submitted with an application to create a new primary single- or multiple-unit dwelling;
One block from a car-share vehicle; or
On-street parking permits are required but not offered to ADU occupant.
Garage conversion or demolition: no replacement parking required.
Owner occupancyADUs: not required.
JADUs: required only if the JADU shares sanitation facilities with the primary dwelling; not required with separate sanitation.
Short-term rentals: ADUs and JADUs may not be rented for less than 31 consecutive days.
Process & timelineMinisterial approval with no discretionary review or hearing, within 60 days of a complete application. Submit a Building Permit application (City permitting portal) and a Deed Restriction application. An ADU submitted with a new primary dwelling is not acted on until the primary dwelling is approved. Making an appointment to meet with a planner in the initial stages of the project can help avoid challenges and is highly recommended.
ExceptionsAppeal process or Waiver and Modifications are at the discretion of the Chief Planner.
Per § 20.350.003(G), setbacks (including front), height, density, lot coverage, FAR and building-separation standards are waived for state-mandated ADUs: converted ADUs on single-unit lots; detached ADUs up to 800 sf on single-unit lots that meet the height limit and 4-foot side and rear setbacks; converted ADUs on existing multifamily lots; and detached ADUs on existing multifamily lots up to 18 feet tall with 4-foot side and rear setbacks. Building, electrical, fire, utility and structural safety codes still apply.
Other local requirementsDeed restriction recorded before the Building Permit (ADUs and JADUs).
Design: local-standards ADUs follow Chapter 20.310 (§ 20.310.003 for detached ADUs and attached ADUs on single-unit lots; § 20.310.004 for attached ADUs on multifamily lots); state-mandated ADUs are exempt.
Separate exterior entry required; a JADU without its own bathroom also needs interior access to the primary dwelling; JADUs need an efficiency kitchen.
Separate electric and water meters required; adequate water and sewer service required.
ADUs may not be sold separately unless allowed under Gov. Code § 66341.
Fire sprinklers not required unless required for the primary dwelling.
Unpermitted ADUs built before January 1, 2020 may apply for legalization or a 5-year delay in enforcement (applications accepted until January 1, 2030).
Tree removals may require a permit.
Local-standards ADUs must meet the zoning district’s development standards; state-mandated ADUs need only meet building, fire and safety codes.
Zones allowedAny district where single-unit and/or multiple-unit dwellings are permitted or conditionally permitted, with an existing dwelling or one proposed along with the ADU.
Minimum lot sizeNone

SB 9: two units or a lot split

Tearing down an old house and building a new one

City demolition permit and local restrictions

Steps every teardown needs (regional and state rules)

Design review, floor area and height for the new house

Published rebuild timelines and fees: beyond what is listed above, the city does not publish a total teardown-to-rebuild timeline or an all-in fee figure on the pages we checked. Not published.

Remodels and additions

Fees the city publishes

Seismic retrofit programs

Electrification rules and PG&E service

Typical cost context (published estimates only)

Not published or not verified

Planning a build, ADU, SB 9 split or remodel?

Tell us about your lot and your goals and request a free, no-obligation consultation. We can help you sort out which permits and rules apply before you hire a designer or builder.

Get a free build/remodel consultation

Bay Build Guide is an information service, not a licensed contractor. We do not perform construction.

Sources

Every item was checked on the date shown. Rules change, so confirm with the city before you design or apply.

  1. San Mateo County ADU Resource Center (21 Elements): South San Francisco local ADU rules (source page updated October 30, 2026) · last checked 2026-11-18
  2. City of South San Francisco: Building Division · last checked 2026-11-18 (this official page blocks automated checks, so we read it through a search engine’s indexed copy)
  3. California HCD: ADU Handbook (March 2026, PDF) · last checked 2026-11-18
  4. California HCD: Accessory Dwelling Units (state ADU program page) · last checked 2026-11-18
  5. City of South San Francisco: SB 9 General Information handout (2024, PDF) · last checked 2026-11-18 (this official page blocks automated checks, so we read it through a search engine’s indexed copy)
  6. California HCD: SB 9 Fact Sheet (PDF) · last checked 2026-11-18
  7. City of South San Francisco: Plan Submittal & Permit Requirements · last checked 2026-11-18 (this official page blocks automated checks, so we read it through a search engine’s indexed copy)
  8. City of South San Francisco: Trees · last checked 2026-11-18 (this official page blocks automated checks, so we read it through a search engine’s indexed copy)
  9. South San Francisco Municipal Code Chapter 13.30: Tree Preservation · last checked 2026-11-18
  10. Bay Area Air District: Asbestos Frequently Asked Questions (PDF) · last checked 2026-11-18
  11. Bay Area Air District: Regulation 11, Rule 2 (asbestos demolition, renovation) · last checked 2026-11-18
  12. U.S. EPA: Lead Renovation, Repair and Painting (RRP) Program · last checked 2026-11-18
  13. PG&E: Gas Service Projects (gas disconnect guide, PDF) · last checked 2026-11-18
  14. PG&E: Building and Renovation Services · last checked 2026-11-18
  15. 2025 California Residential Code, Chapter 1 (Section R105 Permits), via UpCodes · last checked 2026-11-18
  16. California Education Code §17620 (school facility fees on residential construction) · last checked 2026-11-18 (this official page blocks automated checks, so we read it through a search engine’s indexed copy)
  17. California Residential Mitigation Program: Check your eligibility (Earthquake Brace + Bolt, Earthquake Soft-Story) · last checked 2026-11-18
  18. California Residential Mitigation Program: Program ZIP code search · last checked 2026-11-18
  19. WestLight Energy (San Mateo County community energy provider): Reach Codes · last checked 2026-11-18
  20. County of San Mateo: Summary of New Construction Reach Code (PDF) · last checked 2026-11-18