Building, remodeling or rebuilding a home in San Bruno, CA
On this page: Contacts · ADUs & JADUs · SB 9 · Tear down & rebuild · Remodels & additions · Fees · Seismic · Electrification & PG&E · Cost context · Not published · Sources
Building and planning contacts
- Community Development: (650) 616-7074; building@sanbruno.ca.gov (permitting); planning@sanbruno.ca.gov (standards). Per the ADU Resource Center. [1]
- Building Division. [2]
ADU contact listed by the county ADU Resource Center: Community Development Department, (650) 616-7074
For permitting procedure questions, reach out to building@sanbruno.ca.gov
For development standards, reach out to planning@sanbruno.ca.gov
Local ADU Website
ADU Ordinance [1]
ADU and JADU rules
This table is from the San Mateo County ADU Resource Center (run by 21 Elements, a partnership of the county’s cities and the County), page updated August 26, 2026 [1]. Confirm details with the city before you design.
| Size | Min: 150 sf – size required by Health Code, section 17958.1 Max one bedroom or less: 850 square feet Max one bedroom or more (Lots less than 7,500 SF): 1,000 SF Max two+ bedrooms ( Lots greater than 7500 square feet): . 1,200 square feet Max JADU: 500 square feet *50% of main home floor area, unless under 800 square feet (state law allows an ADU up to 800 square feet on every property, some exceptions |
|---|---|
| Height | Detached ADU on a single-family lot or single-story multifamily lot: 16 feet (+2 feet allowed for roof-pitch alignment) Multi-story multifamily, or any lot within ½ mile of a major transit stop/high-quality transit corridor: 18 feet (+2 feet allowed for roof-pitch alignment) Attached ADUs: follow the primary dwelling’s height limit, max 2 stories ADUs over a legally established detached garage: up to 25 feet |
| Setbacks | Rear and side: 4 feet |
| Parking | JADUs: No parking required ADUs: One spot may be required (tandem allowed). No parking required if ADU is: within ½ mile walking distance from public transit part of the existing/proposed primary residence, multifamily structure, or an existing accessory structure state-exempt ADU (falls under a Government Code §66323 category) in a historic district, or one block from a car-share vehicle On-street parking permits are required but not offered to ADU occupant |
| Owner occupancy | JADU: Required, ADU: not required for ADUs built recently (2020-2024) |
| Process & timeline | Apply for a building permit. Deed restriction required prior to issuing building permit. Making an appointment to meet with a planner in the initial stages of the project can help avoid challenges and is highly recommended. |
| Exceptions | ADUs under 800 square feet are exempt from FAR, impervious surface, lot size, and lot coverage requirements. |
| Other local requirements | Only one ADU per property is allowed for single family lots. No drainage or topographic maps required. ADUs must comply with all requirements of the underlying zoning district. No short term rentals. Aircraft Noise Insulation requirement: ADUs in 65+ CNEL zones near SFO must meet Aircraft Noise Insulation Program standards. |
| Zones allowed | ADUs are permitted in any district where residential uses are permitted |
| Minimum lot size | 0 |
- State baseline (all California cities): the city must approve or deny a complete ADU/JADU application within 60 days when there is an existing home; JADUs are limited to 500 sq ft inside the home; and ADUs of 750 sq ft or less pay no impact fees. [3][4]
SB 9: two units or a lot split
- The SB 9 application requires each new lot to be at least 1,200 sq ft and at least 40% of the original lot, with an affidavit to live in one unit for three years. [5]
- State rules (SB 9): ministerial approval of up to two units on a single-family lot, or a split into two lots of roughly equal size (neither under 40%, each generally at least 1,200 sq ft); the city must allow units of at least 800 sq ft; no demolition of rent-controlled, deed-restricted affordable or recently tenant-occupied housing; lot-split applicants sign a three-year owner-occupancy affidavit. [6]
Tearing down an old house and building a new one
City demolition permit and local restrictions
- A separate demolition permit is required, with a site plan showing structures and trees and how trees will be protected or removed. [7]
- Removing a heritage tree needs a separate heritage tree permit, even when it goes with a building or planning permit. [8]
Steps every teardown needs (regional and state rules)
- Air District “J number.” Every demolition of a load-bearing structure needs a Bay Area Air District demolition notification (J number), regardless of asbestos content, at least 10 working days before work starts; for buildings with four or fewer units, 72-hour notice is allowed for an extra fee. Cities require the J number before issuing a demolition permit. [9][10]
- Asbestos. For homes with four or fewer units, a full asbestos survey is not required, but specific materials (HVAC ducting, acoustic ceilings or plaster, textured walls, cement siding or stucco, resilient flooring) must be sampled and tested if they will be disturbed. [9]
- Lead paint. Renovation, repair and painting work that disturbs paint in homes built before 1978 is covered by EPA’s lead-safe RRP rule, which requires certified firms. [11]
- Gas and electric disconnect. Request the disconnect through PG&E Building and Renovation Services (Your Projects). PG&E removes the meter and cuts gas service at the main or property line. [12][13]
- Water and sewer. Water meter removal and sewer lateral capping are handled by your water provider and sewer agency; specific steps are listed above only where the city publishes them. Otherwise, the steps are not published on the city pages we checked.
Design review, floor area and height for the new house
- Planning applications that can apply to new homes are listed on the Planning Applications page. [14]
Published rebuild timelines and fees: beyond what is listed above, the city does not publish a total teardown-to-rebuild timeline or an all-in fee figure on the pages we checked. Not published.
Remodels and additions
- Building Division permit information. [2]
- The California Residential Code that cities adopt (Section R105) requires a permit to build, enlarge, alter, repair, move or demolish a home or to change its electrical, gas, mechanical or plumbing systems. Section R105.2 exempts minor work such as painting, papering, tiling, carpeting, cabinets and countertops. Cities can amend these rules. Whether a job is issued over the counter or online or needs full plan check depends on the city, so ask the building division. [15]
Fees the city publishes
- Sample ADU permit fees reported for recent permits: ADU 1(426 sf, internal conversion): $2,825
ADU 2 (562 sf, detached): $4,456
No impact fees for ADUs/JADUs [1] - Per the ADU Resource Center, San Bruno charges no impact fees for ADUs/JADUs. [1]
- School impact fees are set by your school district, not the city. Residential additions of 500 sq ft or less are exempt under Education Code §17620; check your district for the current rate. [16]
- ADU impact fee waiver: no impact fees on ADUs of 750 sq ft or less or JADUs of 500 sq ft or less; larger ADUs pay in proportion to the main home’s size. [3]
Seismic retrofit programs
- Earthquake Brace + Bolt (EBB): grants of up to $3,000 toward a code-compliant retrofit for houses built before 1980 with a raised foundation or crawl space, in eligible ZIP codes, with a supplemental grant for households earning $94,480 or less. Registration opens in rounds, so check your ZIP. [17][18]
- Earthquake Soft-Story (ESS): grants of up to $13,000 for qualifying homes with living space over a garage or open ground floor. [17]
- No mandatory soft-story retrofit ordinance was found for this city on the pages checked. [17]
Electrification rules and PG&E service
- WestLight Energy (the county’s community energy provider) lists San Bruno among San Mateo County jurisdictions with a reach code. Some reach codes require all-electric new construction, while newer ones use energy-performance targets instead. San Mateo County’s own 2025 reach code, for example, no longer mandates all-electric. Ask the building division which version applies to your permit date. [19][20]
- New or upgraded service: new electric and gas service, service upgrades (for example for an all-electric home or EV charging) and relocations are requested through PG&E Building and Renovation Services. Apply early, because utility work is often on the critical path. [13][21]
Typical cost context (published estimates only)
- The San Mateo County ADU Resource Center gives a very rough placeholder of $450–$600 per sq ft for ADU construction plus design and fees. Hard costs are typically about 85% of the budget, ranging from about $30,000 for a simple interior conversion to $400,000+ for a large hillside detached ADU. Kitchens run $25,000–$50,000 and bathrooms $15,000–$25,000 each. These are estimates, not quotes. [22]
- For new custom homes, full rebuilds and large additions, no city in this batch publishes a cost-per-square-foot figure, so we do not quote one. Get written bids based on your plans. [22]
Not published or not verified
- Fee schedule and design review triggers were not checked.
Planning a build, ADU, SB 9 split or remodel?
Tell us about your lot and your goals and request a free, no-obligation consultation. We can help you sort out which permits and rules apply before you hire a designer or builder.
Get a free build/remodel consultationSources
- San Mateo County ADU Resource Center (21 Elements): San Bruno local ADU rules (source page updated August 26, 2026)
- City of San Bruno: Building Division
- California HCD: ADU Handbook (March 2026, PDF)
- California HCD: Accessory Dwelling Units (state ADU program page)
- City of San Bruno: SB 9 application (PDF)
- California HCD: SB 9 Fact Sheet (PDF)
- City of San Bruno: Demolition Permits (PDF)
- City of San Bruno: Trees on Private Property
- Bay Area Air District: Asbestos Frequently Asked Questions (PDF)
- Bay Area Air District: Regulation 11, Rule 2 (asbestos demolition, renovation)
- U.S. EPA: Lead Renovation, Repair and Painting (RRP) Program
- PG&E: Gas Service Projects (gas disconnect guide, PDF)
- PG&E: Building and Renovation Services
- City of San Bruno: Planning Applications
- 2025 California Residential Code, Chapter 1 (Section R105 Permits), via UpCodes
- California Education Code §17620 (school facility fees on residential construction)
- California Residential Mitigation Program: Check your eligibility (Earthquake Brace + Bolt, Earthquake Soft-Story)
- California Residential Mitigation Program: Program ZIP code search
- WestLight Energy (San Mateo County community energy provider): Reach Codes
- County of San Mateo: Summary of New Construction Reach Code (PDF)
- PG&E: Building and Renovation application resources
- San Mateo County ADU Resource Center: Budgeting & Finance