Building, remodeling or rebuilding a home in Hillsborough, CA
On this page: Contacts · ADUs & JADUs · SB 9 · Tear down & rebuild · Remodels & additions · Fees · Seismic · Electrification & PG&E · Cost context · Not published · Sources
Building and planning contacts
- Planning Division: (650) 375-7422 (per the ADU Resource Center). [1]
- Building permits are applied for through the Town’s online permit portal. [2]
ADU contact listed by the county ADU Resource Center: Planning Division – 650.375.7422
Local ADU Website
ADU Ordinance [1]
ADU and JADU rules
This table is from the San Mateo County ADU Resource Center (run by 21 Elements, a partnership of the county’s cities and the County), page updated October 23, 2026 [1]. Confirm details with the city before you design.
| Size | JADU: 500 sq. ft. Class 1 ADUs: 800 sq. ft. Class 2 Detached/Attached ADUs (one bedroom or less): 850 sq. ft. Class 2 Detached/Attached ADUs (2+ bedrooms): 1,000 sq. ft. An attached ADU on a lot with an existing primary home is limited to 50% of the primary home. Applicant can request an ADU Exception Review, which allows more permissive standards through a discretionary review process. |
|---|---|
| Height | Detached: Up to 16 feet. If site is within ½ mile walking of transit, then 18 feet is allowed (Up to 20 feet if necessary to accommodate a roof pitch that aligns with the roof pitch of the primary home) Detached with increased setbacks: Up to 22 feet, if ADU has side and rear setbacks of at least 20 feet and is at least 25 feet from all public right-of-way. Attached: Up to the maximum height allowed in the underlying zone of the primary dwelling or 25 feet, whichever is lower. An attached ADU may not exceed 2 stories. |
| Setbacks | Side and Rear: 4 feet Front: 20 feet, unless these would preclude the construction of an ADU that is 800 square feet No setback is required for an ADU that is constructed in the same location and to the same dimensions as an existing structure |
| Parking | JADUs: No parking required For Class 2 ADUs: One off-street parking space is required for each ADU or bedroom, whichever is less (tandem or within setback allowed). No parking required if: ½ mile walking distance from public transit, in a historic district, or one block from a car-share vehicle, or on-street parking permits are required but not offered to ADU occupant when the ADU application is submitted with an application to create a new primary dwelling |
| Owner occupancy | JADU: Required, unless the JADU has separate sanitation facilities (i.e. does not share sanitation facilities with the existing primary dwelling unit structure) or if the property is entirely owned by another governmental agency, land trust, or housing organization. |
| Process & timeline | Please contact our ADU Specialist via email at adu@hillsborough.net, or make an appointment here (https://outlook.office365.com/book/VirtualADUSpecialistBooking@hillsborough.net/s/ ZOlGkmYc7UmoPbxPIIwf5w2). |
| Exceptions | Applicant can request an ADU Exception Review, which allows more permissive standards through a discretionary review process. An ADU or JADU that does not comply with every applicable objective standard may be approved through a staff-level the design review. |
| Other local requirements | ADUs must comply with Building and Fire Code requirements. No short-term rentals (less than 30-days). ADU Planning permits subject to all objective standards, including Architecture and Landscaping Requirements. Additional requirements may apply if: the site is within a HFSZ or WUI Zone the structure is or lot contains a historic resource the ADU or necessary site work is within 20 feet of the top of bank of a creek |
| Zones allowed | Class 1 ADUs (66323 units) allowed in residential or mixed-used zones Class 2 ADUs (66314 units) allowed in single family and multi family residential zones JADU allowed in single family residential zones |
| Minimum lot size | None |
- State baseline (all California cities): the city must approve or deny a complete ADU/JADU application within 60 days when there is an existing home; JADUs are limited to 500 sq ft inside the home; and ADUs of 750 sq ft or less pay no impact fees. [3][4]
SB 9: two units or a lot split
- SB 9 projects are approved ministerially when they meet state law and the Town’s objective standards. [5]
- State rules (SB 9): ministerial approval of up to two units on a single-family lot, or a split into two lots of roughly equal size (neither under 40%, each generally at least 1,200 sq ft); the city must allow units of at least 800 sq ft; no demolition of rent-controlled, deed-restricted affordable or recently tenant-occupied housing; lot-split applicants sign a three-year owner-occupancy affidavit. [6]
Tearing down an old house and building a new one
City demolition permit and local restrictions
- Hillsborough treats a teardown and new house as an ADRB-level project. The order of demolition versus design approval was not spelled out on the pages checked; confirm with Planning before scheduling demolition. [7][8]
Steps every teardown needs (regional and state rules)
- Air District “J number.” Every demolition of a load-bearing structure needs a Bay Area Air District demolition notification (J number), regardless of asbestos content, at least 10 working days before work starts; for buildings with four or fewer units, 72-hour notice is allowed for an extra fee. Cities require the J number before issuing a demolition permit. [9][10]
- Asbestos. For homes with four or fewer units, a full asbestos survey is not required, but specific materials (HVAC ducting, acoustic ceilings or plaster, textured walls, cement siding or stucco, resilient flooring) must be sampled and tested if they will be disturbed. [9]
- Lead paint. Renovation, repair and painting work that disturbs paint in homes built before 1978 is covered by EPA’s lead-safe RRP rule, which requires certified firms. [11]
- Gas and electric disconnect. Request the disconnect through PG&E Building and Renovation Services (Your Projects). PG&E removes the meter and cuts gas service at the main or property line. [12][13]
- Water and sewer. Water meter removal and sewer lateral capping are handled by your water provider and sewer agency; specific steps are listed above only where the city publishes them. Otherwise, the steps are not published on the city pages we checked.
Design review, floor area and height for the new house
- New homes and substantial remodels go to the ADRB: a required pre-application meeting with a planner, then preliminary and formal design review, submitted digitally. [7][14][8]
Published rebuild timelines and fees: beyond what is listed above, the city does not publish a total teardown-to-rebuild timeline or an all-in fee figure on the pages we checked. Not published.
Remodels and additions
- Smaller remodels may be reviewed at staff level; larger ones go to ADRB. The Application Procedures page explains the levels. [7]
- The California Residential Code that cities adopt (Section R105) requires a permit to build, enlarge, alter, repair, move or demolish a home or to change its electrical, gas, mechanical or plumbing systems. Section R105.2 exempts minor work such as painting, papering, tiling, carpeting, cabinets and countertops. Cities can amend these rules. Whether a job is issued over the counter or online or needs full plan check depends on the city, so ask the building division. [15]
Fees the city publishes
- Sample ADU permit fees reported for recent permits: ADU 1 (2019, 674 sf, detached): $4,800
ADU 2 (2019, 437 sf, detached): $3,400
No impact fees if ADU is under 750 square feet [1] - School impact fees are set by your school district, not the city. Residential additions of 500 sq ft or less are exempt under Education Code §17620; check your district for the current rate. [16]
- ADU impact fee waiver: no impact fees on ADUs of 750 sq ft or less or JADUs of 500 sq ft or less; larger ADUs pay in proportion to the main home’s size. [3]
Seismic retrofit programs
- Earthquake Brace + Bolt (EBB): grants of up to $3,000 toward a code-compliant retrofit for houses built before 1980 with a raised foundation or crawl space, in eligible ZIP codes, with a supplemental grant for households earning $94,480 or less. Registration opens in rounds, so check your ZIP. [17][18]
- Earthquake Soft-Story (ESS): grants of up to $13,000 for qualifying homes with living space over a garage or open ground floor. [17]
- No mandatory soft-story retrofit ordinance was found for this city on the pages checked. [17]
Electrification rules and PG&E service
- WestLight Energy (the county’s community energy provider) lists Hillsborough among San Mateo County jurisdictions with a reach code. Some reach codes require all-electric new construction, while newer ones use energy-performance targets instead. San Mateo County’s own 2025 reach code, for example, no longer mandates all-electric. Ask the building division which version applies to your permit date. [19][20]
- New or upgraded service: new electric and gas service, service upgrades (for example for an all-electric home or EV charging) and relocations are requested through PG&E Building and Renovation Services. Apply early, because utility work is often on the critical path. [13][21]
Typical cost context (published estimates only)
- The San Mateo County ADU Resource Center gives a very rough placeholder of $450–$600 per sq ft for ADU construction plus design and fees. Hard costs are typically about 85% of the budget, ranging from about $30,000 for a simple interior conversion to $400,000+ for a large hillside detached ADU. Kitchens run $25,000–$50,000 and bathrooms $15,000–$25,000 each. These are estimates, not quotes. [22]
- For new custom homes, full rebuilds and large additions, no city in this batch publishes a cost-per-square-foot figure, so we do not quote one. Get written bids based on your plans. [22]
Not published or not verified
- Hillsborough’s demolition checklist and fee schedule were not checked.
Planning a build, ADU, SB 9 split or remodel?
Tell us about your lot and your goals and request a free, no-obligation consultation. We can help you sort out which permits and rules apply before you hire a designer or builder.
Get a free build/remodel consultationSources
- San Mateo County ADU Resource Center (21 Elements): Hillsborough local ADU rules (source page updated October 23, 2026)
- Town of Hillsborough: Building Division
- California HCD: ADU Handbook (March 2026, PDF)
- California HCD: Accessory Dwelling Units (state ADU program page)
- Town of Hillsborough: SB 9 & 10
- California HCD: SB 9 Fact Sheet (PDF)
- Town of Hillsborough: Application Procedures
- Town of Hillsborough: Planning Applications
- Bay Area Air District: Asbestos Frequently Asked Questions (PDF)
- Bay Area Air District: Regulation 11, Rule 2 (asbestos demolition, renovation)
- U.S. EPA: Lead Renovation, Repair and Painting (RRP) Program
- PG&E: Gas Service Projects (gas disconnect guide, PDF)
- PG&E: Building and Renovation Services
- Town of Hillsborough: Architectural Project Design Review application & checklist (PDF)
- 2025 California Residential Code, Chapter 1 (Section R105 Permits), via UpCodes
- California Education Code §17620 (school facility fees on residential construction)
- California Residential Mitigation Program: Check your eligibility (Earthquake Brace + Bolt, Earthquake Soft-Story)
- California Residential Mitigation Program: Program ZIP code search
- WestLight Energy (San Mateo County community energy provider): Reach Codes
- County of San Mateo: Summary of New Construction Reach Code (PDF)
- PG&E: Building and Renovation application resources
- San Mateo County ADU Resource Center: Budgeting & Finance