Building, remodeling or rebuilding a home in Foster City, CA
On this page: Contacts · ADUs & JADUs · SB 9 · Tear down & rebuild · Remodels & additions · Fees · Seismic · Electrification & PG&E · Cost context · Not published · Sources
Building and planning contacts
- Building: Building@fostercity.org. Planning: Planning@fostercity.org. [1]
- Building permits overview. [2]
ADU contact listed by the county ADU Resource Center: Email Building Department: Building@fostercity.org
Email Planning Department: Planning@fostercity.org
Local ADU Website
ADU Ordinance [1]
ADU and JADU rules
This table is from the San Mateo County ADU Resource Center (run by 21 Elements, a partnership of the county’s cities and the County), page updated October 22, 2026 [1]. Confirm details with the city before you design.
| Size | Min:150 square feet Max ADU in single-family zoning districts: 1200 square feet or 50% of main home floor area (whichever is less), unless under 800 square feet (state law allows an ADU up to 800 square feet on every property, some exceptions may apply); ADU may be capped at up to 850sf in some cases Max ADU in multi-family zoning districts: For conversion ADUs, 850 square feet for one bedroom, 1000 square feet for two or more bedrooms. For attached ADUs, 1200 square feet or 50% of the existing or proposed primary dwelling, whichever is less. Max ADU in PF districts: For conversion ADUs, 850 square feet for a studio or one bedroom, or 1000 square feet for two or more bedrooms. For attached/detached ADUs, 850 square feet for a studio or one bedroom, or 1200 square feet for two or more bedrooms. Max JADU: 500 square feet |
|---|---|
| Height | JADU – Within existing structure Attached ADU: Shall not exceed 25 feet in height, or the height of the primary dwelling, whichever is lower. ADUs shall not exceed two stories in height. Detached ADU: 16 feet, except within ½ mile of major transit stop or high-quality transit corridor – 18 feet; 2 feet may be added to align with roof pitch of primary dwelling; 18 feet maximum for multi-family, multi-story ADU |
| Setbacks | Side and Rear: 4 feet Front: may not be located in the front yard, unless development of an eight hundred-fifty-square-foot ADU is otherwise infeasible. |
| Parking | JADUs: No parking required ADUs: One spot may be required (tandem allowed). No parking required if: The ADU is located within one-half mile walking distance of public transit. The ADU is a conversion ADU. When there is an approved car share vehicle for which a Foster City business license has been issued and remains active, located within one block of the accessory dwelling unit. ADU that only includes a studio with no bedroom. The ADU is located within an architecturally and historically significant area. |
| Owner occupancy | JADU: The property owner must reside in either the remaining portion of the primary dwelling unit or the JADU. Owner occupancy shall not be required if the owner is another governmental agency, land trust, or housing organization. |
| Process & timeline | ADUs are subject to a Building Permit. Making an appointment to meet with a planner and the Building Official in the initial stages of the project can help avoid challenges and is highly recommended. |
| Exceptions | None |
| Other local requirements | Shall comply with the California Building Code JADUs and ADUs shall provide exterior access separate from primary dwelling unit An ADU shall not be required to provide fire sprinklers if they are not required for the primary residence and may employ alternative methods for fire protection. Short term rentals are not allowed ADU must be clearly subordinate to primary dwelling by size, location, and appearance. Sale of JADU separate from the primary dwelling is prohibited (deed restriction required) Number of ADUs: Single family lots: One JADU (up to 500sf), one conversion ADU, and one ADU (up to 850sf); One JADU (up to 500sf) and one ADU (over 850sf) Multi-family lots: Conversion ADUs: No more than twenty-five percent of the existing multifamily dwelling units shall be permitted. Detached ADUs: Up to eight detached ADUs on a multifamily lot with an existing multifamily building, not to exceed the number of existing dwelling units on the lot. Attached ADUs: Limited to one unit per multifamily lot with an existing multifamily building. PF lots: No more than four ADUs and/or JADUs shall be permitted on properties owned or occupied by a religious institution or school use. |
| Zones allowed | Single family lots in R-1, R-2, R-1/PD; multi family lots in R-3, R-4, R-T, C-2, CM; lots in PF |
| Minimum lot size | None |
- State baseline (all California cities): the city must approve or deny a complete ADU/JADU application within 60 days when there is an existing home; JADUs are limited to 500 sq ft inside the home; and ADUs of 750 sq ft or less pay no impact fees. [3][4]
SB 9: two units or a lot split
- SB 9 lot splits are ministerial. The checklist asks for the SB 9 application, ownership verification, a site survey, plans and the parcel map, submitted to Community Development. [5][6]
- State rules (SB 9): ministerial approval of up to two units on a single-family lot, or a split into two lots of roughly equal size (neither under 40%, each generally at least 1,200 sq ft); the city must allow units of at least 800 sq ft; no demolition of rent-controlled, deed-restricted affordable or recently tenant-occupied housing; lot-split applicants sign a three-year owner-occupancy affidavit. [7]
Tearing down an old house and building a new one
City demolition permit and local restrictions
- A building permit is required for demolition and new construction, and a Waste Management Plan must be approved before the permit is issued. [8][2]
- Foster City’s rules for removing trees on private property were not confirmed from an official page. [2]
Steps every teardown needs (regional and state rules)
- Air District “J number.” Every demolition of a load-bearing structure needs a Bay Area Air District demolition notification (J number), regardless of asbestos content, at least 10 working days before work starts; for buildings with four or fewer units, 72-hour notice is allowed for an extra fee. Cities require the J number before issuing a demolition permit. [9][10]
- Asbestos. For homes with four or fewer units, a full asbestos survey is not required, but specific materials (HVAC ducting, acoustic ceilings or plaster, textured walls, cement siding or stucco, resilient flooring) must be sampled and tested if they will be disturbed. [9]
- Lead paint. Renovation, repair and painting work that disturbs paint in homes built before 1978 is covered by EPA’s lead-safe RRP rule, which requires certified firms. [11]
- Gas and electric disconnect. Request the disconnect through PG&E Building and Renovation Services (Your Projects). PG&E removes the meter and cuts gas service at the main or property line. [12][13]
- Water and sewer. Water meter removal and sewer lateral capping are handled by your water provider and sewer agency; specific steps are listed above only where the city publishes them. Otherwise, the steps are not published on the city pages we checked.
Design review, floor area and height for the new house
- New-home design review and floor-area limits were not checked; ask Planning. [2]
Published rebuild timelines and fees: beyond what is listed above, the city does not publish a total teardown-to-rebuild timeline or an all-in fee figure on the pages we checked. Not published.
Remodels and additions
- Foster City’s Building Permits page lists which projects need permits and how to apply. [2]
- The California Residential Code that cities adopt (Section R105) requires a permit to build, enlarge, alter, repair, move or demolish a home or to change its electrical, gas, mechanical or plumbing systems. Section R105.2 exempts minor work such as painting, papering, tiling, carpeting, cabinets and countertops. Cities can amend these rules. Whether a job is issued over the counter or online or needs full plan check depends on the city, so ask the building division. [14]
Fees the city publishes
- Sample ADU permit fees reported for recent permits: Fees are based off of the job valuation. Contact Foster City Building Division by emailing building@fostercity.org
Attached ADU – 2020, 980 sq. ft., $198k, $8032.66 BP Fee Detached ADU – 2021, 564 sq. ft., $200k, $7,600.71 BP Fee
JADU – 2021, 256 sq. ft., $64k, $4649.83 BP Fee [1] - School impact fees are set by your school district, not the city. Residential additions of 500 sq ft or less are exempt under Education Code §17620; check your district for the current rate. [15]
- ADU impact fee waiver: no impact fees on ADUs of 750 sq ft or less or JADUs of 500 sq ft or less; larger ADUs pay in proportion to the main home’s size. [3]
Seismic retrofit programs
- Earthquake Brace + Bolt (EBB): grants of up to $3,000 toward a code-compliant retrofit for houses built before 1980 with a raised foundation or crawl space, in eligible ZIP codes, with a supplemental grant for households earning $94,480 or less. Registration opens in rounds, so check your ZIP. [16][17]
- Earthquake Soft-Story (ESS): grants of up to $13,000 for qualifying homes with living space over a garage or open ground floor. [16]
- No mandatory soft-story retrofit ordinance was found for this city on the pages checked. [16]
Electrification rules and PG&E service
- Foster City is not listed on WestLight Energy’s reach code page, so state energy code minimums likely apply. Confirm with the building division. [18]
- New or upgraded service: new electric and gas service, service upgrades (for example for an all-electric home or EV charging) and relocations are requested through PG&E Building and Renovation Services. Apply early, because utility work is often on the critical path. [13][19]
Typical cost context (published estimates only)
- The San Mateo County ADU Resource Center gives a very rough placeholder of $450–$600 per sq ft for ADU construction plus design and fees. Hard costs are typically about 85% of the budget, ranging from about $30,000 for a simple interior conversion to $400,000+ for a large hillside detached ADU. Kitchens run $25,000–$50,000 and bathrooms $15,000–$25,000 each. These are estimates, not quotes. [20]
- For new custom homes, full rebuilds and large additions, no city in this batch publishes a cost-per-square-foot figure, so we do not quote one. Get written bids based on your plans. [20]
Not published or not verified
- Tree removal rules on private property were not confirmed.
- Fee schedule and design review rules were not checked.
Planning a build, ADU, SB 9 split or remodel?
Tell us about your lot and your goals and request a free, no-obligation consultation. We can help you sort out which permits and rules apply before you hire a designer or builder.
Get a free build/remodel consultationSources
- San Mateo County ADU Resource Center (21 Elements): Foster City local ADU rules (source page updated October 22, 2026)
- City of Foster City: Building Permits
- California HCD: ADU Handbook (March 2026, PDF)
- California HCD: Accessory Dwelling Units (state ADU program page)
- City of Foster City: California Senate Bill (SB) 9
- City of Foster City: SB 9 Urban Lot Split Submittal Checklist (PDF)
- California HCD: SB 9 Fact Sheet (PDF)
- City of Foster City: Construction and Demolition
- Bay Area Air District: Asbestos Frequently Asked Questions (PDF)
- Bay Area Air District: Regulation 11, Rule 2 (asbestos demolition, renovation)
- U.S. EPA: Lead Renovation, Repair and Painting (RRP) Program
- PG&E: Gas Service Projects (gas disconnect guide, PDF)
- PG&E: Building and Renovation Services
- 2025 California Residential Code, Chapter 1 (Section R105 Permits), via UpCodes
- California Education Code §17620 (school facility fees on residential construction)
- California Residential Mitigation Program: Check your eligibility (Earthquake Brace + Bolt, Earthquake Soft-Story)
- California Residential Mitigation Program: Program ZIP code search
- WestLight Energy (San Mateo County community energy provider): Reach Codes
- PG&E: Building and Renovation application resources
- San Mateo County ADU Resource Center: Budgeting & Finance